ENERGY & INDUSTRY..

MARLEY COOLING TOWER

Key Features

Location:
Pajaritos Petrochemical Complex, Coatzacoalcos, Mexico

Operator:
Pemex Petroquimica

Duration:
10 months

Client:
Pemex Petroquimica

Scope:
Multi-disciplinary construction

MARLEY COOLING TOWER

Pemex Petroquimica awarded Kentech Mexico the refurbishment of a 5 cell cooling tower in the Pajaritos Petrochemical Complex in Coatzacoalcos, Mexico.

The scope of work involves the complete overhaul of the tower, including the refurbishment of the fan motors, cooling fans, packing material etc.  All works were successfully executed in 300 days.

During this 300 days, the tower remained in operation as it was required to support the overall plant operation. Pemex released 1 cell at a time to Kentech.

Kentech Mexico have executed several projects on behalf of Pemex Petroquimica in the Coatzacoalcos area, however this was the first to be awarded in the Pajaritos Complex and further strengthens the Kentech presence in the south of Mexico and as a multi-disciplinary construction company in the region.