BRISTOL MYERS SQUIBB, CRUISERATH, DUBLIN

Key Features

Location:
Mulhuddard, Dublin, Ireland

Operator:
Bristol Myers Squibb

Duration:
24 months

Client:
Fluor

Scope:
Provision of a Multipurpose Pharmaceutical Plant on a Greenfield Site at Cruiserath Road, Mulhuddard in Dublin

BRISTOL MYERS SQUIBB, CRUISERATH, DUBLIN

Bristol-Myers Squibb started the construction of a new bulk manufacturing facility in Mulhuddard, Dublin. Kentech played a key role in the construction of the first 3 phases of this $300 million plant. Kentech was awarded the contract to carry out the procurement, installation and testing of the HVAC, electrical and instrumentation systems. The HVAC contract included the 120,000 man hour installation that was completed on schedule.

The work-scope for the HVAC included the following:

  • Development of and co-ordination of all the ductwork fabrication and installation drawings
  • Fabrication and installation of all of the ductwork
  • Procurement and installation of all ductwork ancillary items
  • Installation of all free issue air handling equipment
  • Provision and installation of a complete building management system.
  • Installation of all ductwork insulation
  • Testing, commissioning and handover of all air and water systems

In addition, Kentech provided 450,000 man hours of electrical and instrumentation services for this greenfield pharmaceutical plant and completed the following system installations and commissioning:

  • Temporary site power and lighting installation
  • All MV equipment and all ring main MV cabling
  • All cable containment
  • Fire alarm, lightning protection and general power systems